Plymouth EfW (Energy from Waste) South West Devon Waste Partnership / MVV Environment Devonport Ltd £140m 34 months GHA Livigunn were appointed by Kier Construction Ltd as Lead Construction Designers for the Plymouth EfW facility. Currently in detailed design stage, the plant will deal with a nominal waste capacity of 245,000 tonnes per annum. The facility is located in the North Yard of Devonport Royal Naval Dockyard. The plant will divert 97% of the South West Devon Waste more

Heysham Reactor 8, Reactor Sea Water (RSW) pump pipework and by-pass pipework replacement British Energy / Boulting Nuclear £2.5m British Energy conditions for supply or repair and installation of plant (2005) 32 weeks Civil, Structural & Mechanical Engineering Design, Stress Analysis and Seismic Qualification Replacement of Reactor 8 RSW pipework and minus 9 RSW Quadrants and pipework with High Density Polyethylene (HDPE ). Bypass of existing damaged , buried, fibreglass more

Torness Reactor 1 Reactor Sea Water (RSW) Pipework Replacement British Energy / Boulting Nuclear £850k British Energy conditions of contract for supply or repair and installation of plant (2005). 30 weeks Civil , Structural & Mechanical Engineering Design, Stress Analysis and Seismic Qualification Replacement of Reactor 1 RSW pump pipework and Minus 9 level distribution pipework for quadrants A, B, C & D in HDPE. Due to the aggressive nature of the sea water the more

UK Based Power Station - Cooling water supply, pipe work replacement Boulting Group Plc £8m Professional Services Contract (Client Specific) 12 months Civil, Structural and Mechanical Engineering The purpose of the project was to replace the entire cast iron pipe work route from within the pump house across site through the turbine hall to the reactor building interface. This was achieved using HDPE pipe with sizes up to 630mm diameter over a distance of 472m. The existing pipe more